Construction Project 2021

We are conducting a $2.5 million construction project during Summer 2021.  The following areas will be addressed as a part of this project:
  • Roof replacement (2 sections)
  • Parking lot drainage improvements and resurfacing (North and South lots)
  • Installation of new chiller
  • Renovation of administrative office area

Please scroll down to view pictures of ongoing progress and important documents.

IMPORTANT DOCUMENTS:
Notice of Hearing on Proposed Sixth Amendment to Lease

Notice of Intent to Sell Bonds  (April 2021)




Construction Image
(7/21/21)  Reinforcing roof area for placement of new chiller (installation expected Oct. 2021)


Construction Image
(7/21/21) Prepping back parking lot for drainage and structural improvements.


Construction Image
(7/21/21) Prepping back parking lot for drainage and structural improvements.


Construction Image
(7/21/21) Prepping front parking lot for drainage improvements.



Construction Image
(7/21/21) Removal and replacement of roof over Middle School.




Construction Images

(7/21/21) New Paint and Carpet in high school offices.


Construction Images
(7/21/21) New paint and carpet in corporation offices.




Construction Images
(7/21/21) Remodel of existing offices to create more individual office space.



Construction Images
(7/21/21)  Creation of new Corporation Office Wing.



Construction Image
(7/27/21) New Drainage System in back lot.



Construction Image

(7/27/21) New Drainage System in back lot.



Construction Image

(7/27/21) New Drainage System in back lot.



Construction Image

(7/27/21) New Drainage System in back lot.



Construction Image


(7/27/21)  Milling front parking lot.


Construction Image


(7/27/21) Milling in front parking lot.